Relating to the interconnection process; and prescribing an effective date.
Allows a person to contract with a third-party consultant to conduct a study or engineering evaluation that a public utility requires for an application to interconnect a microgrid or community microgrid. Allows a contracted third-party consultant to receive from a public utility all technical data necessary to conduct the study or engineering evaluation and submit to the public utility a preliminary design for review. Requires a public utility to approve or deny an applic…
- Introduced
- 2025-01-13
- Cosponsors
- 0
- Policy area
- Energy
- Latest action
- 2025-08-07: Chapter 471, (2025 Laws): Effective date September 26, 2025.